Tennessee Gas Pipeline/Keyspan Energy

Tennessee Gas Pipeline/Keyspan Energy

Location: Nashua, NH

Transgas provided temporary LNG storage, transportation, and vaporization to support approximately 40,000 residential and commercial customers in the Nashua, NH service territory of Keyspan while routine service was being performed. 6 to 9 loads were delivered daily.

Dates: 21 Days, July 2002
Principle in Charge: John Sorota
Project Team Participants: J. Sorota and D. Batts
Vaporizer Equipment: (3) Heated Vaporizers, (4) Ambient 60 MCFH vaporizers
Peak flow: 7200 MCFD
Project Status: Completed