Seaside Energy LLC for Woodland Pulp Mill

Baileyville, ME

Location: Baileyville, ME

Transgas provided temporary LNG storage and transportation to an industrial customer that was converting from fuel oil to natural gas. 5 to 6 loads were delivered to the site daily while the mill was tying into the Maritime pipeline. In total, 797 loads of LNG were delivered.

Dates: May to December 2011
Principle in Charge: John Sorota
Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, R. Bevens, H. Bond and E. Kellstrom
Project Status: Completed

National Grid

Location: Rotterdam Junction, NY

Transgas responded to an emergency situation in Rotterdam Junction, NY, where hurricane flooding washed away the existing natural gas pipeline. Transgas responded by providing temporary LNG storage, transportation, and vaporization to the site to provide gas to over 500 customers and a large chemical plant.

Dates: September to December 2011

Principle in Charge: John Sorota

Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, R. Bevens, H. Bond and E. Kellstrom

Vaporizer Equipment: (2) Ambient 60 MCFH vaporizers

Peak flow: 414 MCFD

Project Status: Completed

Tennessee Gas Pipeline/Keyspan Energy

Tennessee Gas Pipeline/Keyspan Energy

Location: Nashua, NH

Transgas provided temporary LNG storage, transportation, and vaporization to support approximately 40,000 residential and commercial customers in the Nashua, NH service territory of Keyspan while routine service was being performed. 6 to 9 loads were delivered daily.

Dates: 21 Days, July 2002
Principle in Charge: John Sorota
Project Team Participants: J. Sorota and D. Batts
Vaporizer Equipment: (3) Heated Vaporizers, (4) Ambient 60 MCFH vaporizers
Peak flow: 7200 MCFD
Project Status: Completed

Duke Energy/Yankee Gas Co.

Location: New London, CT

Transgas provided temporary LNG storage, transportation, and vaporization to support approximately 7000 residential and commercial customers while routine maintenance was performed on the line.

Dates: 3 days, August 2005
Principle in Charge: John Sorota
Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, and E. Kellstrom
Vaporizer Equipment: (3) Ambient 60 MCFH vaporizers
Peak flow: 2,000 MCFD
Project Status: Completed

Tennessee Gas Pipeline/Yankee Gas Co.

Tennessee Gas Pipeline/Yankee Gas Co.Location: Torrington, CT

Transgas provided temporary LNG storage, transportation, and vaporization to support approximately 7090 residential and commercial customers while the Tennessee Gas Pipeline Company performed routine maintenance on the line.

Dates: 7 days, August 2002
Principle in Charge: John Sorota
Project Team Participants: J. Sorota and D. Batts
Vaporizer Equipment: (4) Ambient 60 MCFH vaporizers
Peak flow: 2321 MCFD
Project Status: Completed

Tennessee Gas Pipeline/UNITIL

Tennessee Gas Pipeline/UNITIL

Location: Fitchburg, MA

Transgas provided temporary LNG storage, transportation, and vaporization to support the towns of Lunenburg, Fitchburg, Westminster, Gardner, Townsend, and Ashby while 5.5 miles of 6” pipe was replaced with 12” pipe. Severe weather prolonged this job.

Dates: May to August 2009
Principle in Charge: John Sorota
Project Team Participants: T. Mehan, D. Batts, J. Sorota, M. Janak, R. Bevens and E. Kellstrom
Vaporizer Equipment: (2) Heated Vaporizers, (2) Ambient 60 MCFH vaporizers
Peak flow: 2520 MCFD
Project Status: Completed

Algonquin Gas Transmission/Keyspan Energy

Algonquin Gas Transmission/Keyspan Energy

Location: Braintree, MA

Transgas provided temporary LNG storage, transportation, and vaporization to support residential and commercial customers in the Braintree, MA service territory of Keyspan while routine service was being performed. 3 to 8 loads of LNG were delivered daily.

Dates: May 2001 – August 2001
Principle in Charge: John Sorota
Project Team Participants: J. Sorota and D. Batts
Vaporizer Equipment: (3) Heated Vaporizers, (4) Ambient 60 MCFH vaporizers
Peak flow: 6500 MCFD
Project Status: Completed